Despite 90 degree temperatures this week, various lift maintenance projects and King Pine terminal construction press on. 

This week, the lift maintenance crew has been working on the following: 

  • Line work on Skyline and SuperQuad
  • Sheave assembly maintenance on Snubber, West Mountain, and Double Runner
  • Electrical work on SuperQuad
  • Hold down assembly maintenance on West Mountain mid-station
  • King Pine tower inspections plus concrete for the new foundation 

While having an outdoor office during the peak of summer has its drawbacks, the upside includes fresh mountain air, top-notch views, and plenty of wildlife sightings. Below are a few photos, sent in recently by some of our Lift Mechanics.